AFRAM Corporation was part of the team lead by Black & Veatch Corporation on the Coldwater Treatment Plant Improvements located in North St. Louis County for the Metropolitan Sewer District.
AFRAM was responsible for the development of the conceptual cost estimate based on preliminary site plans and sketches. AFRAM managed the coordination of meetings with the design team and identified the goals and strategy for each estimating stage, and followed MSD pricing and procedures for equipment and instrumentation. AFRAM identified general conditions coordinated meetings with subcontractors, suppliers and the lead architect to review drawings, overhead, costs, and profit margin.
• Demolition and new construction of influent pump station.
• Demolition and new construction of grip pump station.
• Modified existing three selector basins and constructed new clarifier.
• Modified aeration basin influent header and aeration house.
• Demolition and new construction of maintenance and blower buildings.
• Constructed gravity thickener and odor control facility.
• Demolition and new construction of site piping and entrance roads.
|
|